Construction Schedule
| Start | Completion | |
| Dejope Hall | February 2011 | June 2012 |
| Lakeshore Hall - Phase 2 | May 2012 | July 2013 |
| Gordon Dining and Event Center | ||
| Phase One | February 2011 | June 2012 |
| Phase Two | September 2012 | October 2013 |
| Carson Gulley | May 2012 | May 2013 |
| Elizabeth Waters Hall | ||
| Dining | May 2013 | November 2013 |
| Residence Hall - Phase One | May 2013 | August 2013 |
| Residence Hall - Phase Two | May 2014 | August 2014 |
| Holt Commons | May 2012 | June 2013 |
| Kronshage Hall | ||
| West | May 2014 | August 2014 |
| East | May 2015 | August 2015 |
| Slichter Hall | May 2015 | August 2015 |
| Witte Hall | 2016 and 2017 | |
| Sellery Hall | 2018 and 2019 | |
| Construction/Renovation Completed | ||
| Smith Hall | November 2004 | August 2006 |
| Ogg Hall | April 2006 | August 2007 |
| Chadbourne Hall | May 2009 | August 2010 |
| Barnard Hall | May 2009 | August 2010 |
| Merit Hall | January 2010 | August 2010 |
| Tripp Hall | May 2010 | August 2010 |
| Adams Hall | May 2011 | August 2011 |