University Housing

New 32 Residence Hall

Construction Schedule: May 2012 - July 2013

Building Enclosed

A high-dynamic-range (HDR) panorama of the site preparation in parking lot 32.With winter just around the corner, contractors working on University Housing's newest residence hall (temporarily named New 32 Hall) have successfully enclosed the building. New 32 Residence Hall is now water tight, with almost all windows covered and exterior cinder blocks built. With this step complete, the building's interior is now being heated, allowing construction crews to continue work inside throughout Wisconsin's cold winter months. To date, precast roof panels have been installed, and masonry crews are laying the interior walls on the building's third, fourth, and fifth floors. Temporary lighting has been installed throughout the interior, as well, and New 32's stairwells have begun to be built.

On the exterior, with the roof panels in place, contractors are scheduled to remove the large crane from the construction site next week. Additionally, exterior veneer brick and stone laying has begun in earnest, starting with the north and west facing facades. Overall, the project continues to proceed satisfactorily and on schedule for New 32's August 2013 opening and dedication.

For a live look at the New 32 Hall construction site, check out our live webcam from the roof of Kronshage Residence Hall (Showerman House) to the north of the construction site.

New 32 Hall Construction Site - November 16, 2012

The south exterior at sunset. A construction banner with the south exterior in the background. The southwest exterior at sunset. New 32 towers over Holt Commons, seen here from the northwest. A high dynamic range (HDR) photo of a New 32 Hall construction sign and its north exterior. A crane hook, with the building's north exterior in the background. New 32 Hall's exterior, seen from the southeast. A high dynamic range (HDR) photo of the large crane. The main lobby. The main lounge on the lower level. The first floor lounge and attached kitchenette. A first floor hallway. An unfinished room for two residents. Two unfinished rooms for two residents each. Electrical conduit ready to be installed. Temporary heaters warm New 32 Hall's interior.